Business plan 2026–27
How Luton Fitness Park CIC will deliver a free outdoor fitness park this year. The public evidence sits in the proposal; this page is the plan we would attach to a bid.
1. Executive summary
- Organisation
- Luton Fitness Park CIC, company number 17271021. Registered 9 June 2026.
- Mission
- A free, inclusive outdoor fitness park in Luton where people belong and connect through movement.
- Vision
- A town with welcoming outdoor training space that is always open: for physical health, mental health, and safer streets.
- What we do
- We are a community-led Community Interest Company campaigning for Luton’s first purpose-built inclusive outdoor fitness park. Until a site is agreed, the work is research, a verified local petition, council engagement, design, and fundraising.
- Goals for the year
- Agree a preferred park location with Luton Borough Council
- Complete feasibility and secure planning permission and council support
- Submit the first grant and community funding applications
- Reach 2,135 valid petition signatures so the council must debate the petition in full council
- Funding
- Volunteer-run. No capital budget is published until a site is agreed. Construction will not start until funding is secured.
- Contact
- lutonfitnesspark@gmail.com
2. Strategic objectives
Long-term aims. This year's business plan is year one of that strategy.
Strategic objective
A free outdoor fitness park that anyone in Luton can use, with no membership barrier.Year 1 goal
Agree a site with the council, complete feasibility, and raise capital funding for the first park.Strategic objective
Inclusive by design: disabled athletes and newcomers can train alongside everyone else.Year 1 goal
Keep Para Workout equipment, inspired by the Matt Hampson Foundation, in the design and in every funding bid.Strategic objective
A third space that supports safer streets and gives young people a positive place to show up.Year 1 goal
Keep council, youth, and community partners in the conversation, and design for activity and footfall rather than a neglected corner.Strategic objective
Shared prevention: everyday movement that can ease pressure on physical health, mental health, and the NHS over time.Year 1 goal
Use the public proposal and theory of change in every bid, and do not over-claim clinical outcomes.
| Strategic objective | Year 1 goal |
|---|---|
| A free outdoor fitness park that anyone in Luton can use, with no membership barrier. | Agree a site with the council, complete feasibility, and raise capital funding for the first park. |
| Inclusive by design: disabled athletes and newcomers can train alongside everyone else. | Keep Para Workout equipment, inspired by the Matt Hampson Foundation, in the design and in every funding bid. |
| A third space that supports safer streets and gives young people a positive place to show up. | Keep council, youth, and community partners in the conversation, and design for activity and footfall rather than a neglected corner. |
| Shared prevention: everyday movement that can ease pressure on physical health, mental health, and the NHS over time. | Use the public proposal and theory of change in every bid, and do not over-claim clinical outcomes. |
3. Operational objectives
What has to work this year so the organisation stays well run while we chase the site and the money.
Area
FundraisingObjective
Submit the first round of trust, foundation, and community funding bids once a site is in view.Area
FacilitiesObjective
Agree a preferred location from the council’s list, then complete feasibility and planning. Stay open to any central, accessible site the council offers.Area
PeopleObjective
Keep a small core team covering community, governance, strategy, and operations, and recruit volunteers for outreach, events, and content.Area
FinanceObjective
Stay CIC-compliant, keep spending light while we are volunteer-run, and produce a detailed capital budget as soon as a site is agreed.Area
ServicesObjective
Grow verified local petition support, keep the website and campaign materials current, and stay in public conversation with residents.Area
GovernanceObjective
Meet CIC duties, keep the community interest locked in, and report progress in the open.
| Area | Objective |
|---|---|
| Fundraising | Submit the first round of trust, foundation, and community funding bids once a site is in view. |
| Facilities | Agree a preferred location from the council’s list, then complete feasibility and planning. Stay open to any central, accessible site the council offers. |
| People | Keep a small core team covering community, governance, strategy, and operations, and recruit volunteers for outreach, events, and content. |
| Finance | Stay CIC-compliant, keep spending light while we are volunteer-run, and produce a detailed capital budget as soon as a site is agreed. |
| Services | Grow verified local petition support, keep the website and campaign materials current, and stay in public conversation with residents. |
| Governance | Meet CIC duties, keep the community interest locked in, and report progress in the open. |
4. Key performance indicators
A short set of measures we can actually watch. Quantity, time, quality, and cost — not everything that could be counted.
Area
QuantityTarget
2,135 valid petition signaturesHow we measure
On-site petition countWho
Ash, TanWhen
This yearNotes
Luton Borough Council must debate the petition in full council at this threshold. The campaign has already passed 500 signatures.Area
TimeTarget
Preferred site agreed with the councilHow we measure
Written confirmation of location options and a preferred siteWho
AshWhen
Phase 5Notes
Land rights, not cost, were the main hurdle in the first council meeting. We will not lock a design until the site is real.Area
QuantityTarget
First grant applications submittedHow we measure
Bids logged (number, amount asked, outcome)Who
AfsarWhen
After a site is in viewNotes
Bids need a location and a budget. We will not send speculative capital asks without them.Area
QualityTarget
Inclusive design retained in every version of the planHow we measure
Equipment list and bid narrative include accessible kitWho
Ash, AfsarWhen
OngoingNotes
Para Workout equipment is a core requirement, not an optional extra.Area
CostTarget
Detailed capital budget published once a site is agreedHow we measure
Annex budget covering equipment, surfacing, install, and contingencyWho
Tan, AfsarWhen
After feasibilityNotes
No headline cost is published yet. Inventing one would weaken bids.Area
TimeTarget
CIC records and public updates kept currentHow we measure
Companies House filings; news posts after each milestoneWho
Callum, TanWhen
OngoingNotes
Accountability is part of the product, not an afterthought.
| Area | Target | How we measure | Who | When |
|---|---|---|---|---|
| Quantity | 2,135 valid petition signatures | On-site petition count | Ash, Tan | This year |
| Time | Preferred site agreed with the council | Written confirmation of location options and a preferred site | Ash | Phase 5 |
| Quantity | First grant applications submitted | Bids logged (number, amount asked, outcome) | Afsar | After a site is in view |
| Quality | Inclusive design retained in every version of the plan | Equipment list and bid narrative include accessible kit | Ash, Afsar | Ongoing |
| Cost | Detailed capital budget published once a site is agreed | Annex budget covering equipment, surfacing, install, and contingency | Tan, Afsar | After feasibility |
| Time | CIC records and public updates kept current | Companies House filings; news posts after each milestone | Callum, Tan | Ongoing |
5. Finance
We will not invent a capital figure before we have a site. In the first council meeting, land rights were the main hurdle, not cost. A detailed income and expenditure annex will follow feasibility.
Category
Capital — buildWhat it covers
Fitness equipment, inclusive / Para Workout kit, surfacing, installation, signage and QR codes, knife bin, memorial or community features.Category
Revenue — keep it openWhat it covers
Maintenance, repairs, insurance, volunteer coordination, and any hosted sessions or competitions once the park exists.Category
In-kindWhat it covers
Council land and permissions, volunteer time, local business support, and campaign tools we already run (website, petition, brand).
| Category | What it covers |
|---|---|
| Capital — build | Fitness equipment, inclusive / Para Workout kit, surfacing, installation, signage and QR codes, knife bin, memorial or community features. |
| Revenue — keep it open | Maintenance, repairs, insurance, volunteer coordination, and any hosted sessions or competitions once the park exists. |
| In-kind | Council land and permissions, volunteer time, local business support, and campaign tools we already run (website, petition, brand). |
Income we will pursue
- Trust and foundation grants
- Community and small-charity funds
- Local business and CSR support
- Council partnership (land, permissions, in-kind)
- Community fundraising
Contingency: do not let a contract, or start construction, until funding for that phase is in place. If income falls short, we scale the first site rather than open a gap in the budget.
6. Risk
The risks we already know, and what we will do so none of them stays unacceptably high.
Area
SiteRisk
An early option, Moor Park, may have land-use restrictions from historic cricket-pitch use, so the first site may need to be elsewhere.Mitigation
Wait for the council’s location list. Stay open to People’s Park or another central site. Do not spend capital until location and permissions are clear.Area
FundingRisk
Grant income is uncertain. A shortfall would delay construction.Mitigation
Do not start build until funding is secured. Diversify bids. Scale the first site rather than over-promise.Area
PeopleRisk
A small volunteer team can burn out or lose capacity.Mitigation
Clear roles, open volunteer roles, and do not take on delivery we cannot staff.Area
PerceptionRisk
Residents may worry the park will attract antisocial behaviour or vandalism.Mitigation
Design for footfall and activity. Use galvanised steel kit. Publish a maintenance plan. Answer concerns in the open (FAQ).Area
ComplianceRisk
CIC, data protection, and bidding duties if records slip.Mitigation
Governance lead, privacy policy, and public reporting. Keep petition data handling tight.
| Area | Risk | Mitigation |
|---|---|---|
| Site | An early option, Moor Park, may have land-use restrictions from historic cricket-pitch use, so the first site may need to be elsewhere. | Wait for the council’s location list. Stay open to People’s Park or another central site. Do not spend capital until location and permissions are clear. |
| Funding | Grant income is uncertain. A shortfall would delay construction. | Do not start build until funding is secured. Diversify bids. Scale the first site rather than over-promise. |
| People | A small volunteer team can burn out or lose capacity. | Clear roles, open volunteer roles, and do not take on delivery we cannot staff. |
| Perception | Residents may worry the park will attract antisocial behaviour or vandalism. | Design for footfall and activity. Use galvanised steel kit. Publish a maintenance plan. Answer concerns in the open (FAQ). |
| Compliance | CIC, data protection, and bidding duties if records slip. | Governance lead, privacy policy, and public reporting. Keep petition data handling tight. |
7. Monitoring and evaluation
Reports should be short enough to act on. We will watch the handful of KPIs above and change course if a target slips.
- Monthly core-team check-ins against Phase 5 (location and funding).
- Petition count watched against the full-council threshold.
- Public news posts after each milestone.
- Council and partner meetings minuted and followed up.
- Once the park exists: usage, maintenance logs, beneficiary and partner feedback, and an annual impact note.
8. Related documents
Use these with this plan. Do not treat this page as a substitute for the public case or the logic model.
- ProposalThe public case: health, mental health, safer streets, and NHS prevention.
- Theory of ChangeHow inputs become activity, outcomes, and impact.
- TimelineWhat is done, what is in progress, and what comes after funding.
- TeamWho is delivering this, and the volunteer roles still open.